Strategic path installation, following 10 years in the planning , with complex landowner issues and being located within SSSI,SPA & SAC designated land, McGowan Ltd were the preferred path & bridge installation contractor, based on Quality and competitive price.
Location: Aviemore to Kincraig
Type of works: Path & Bridge Construction
Contract Value: £150,000.00
Project Notes:
- Project within Cairngorms National Park
- 3.5km of new 2 metre wide pathways constructed through 3nr estates including 2nr bridges installed
- Protection of overhead powerlines, underground services
- Works adjacent live railway – Change of work methodology adopted in line with Railtrack requirements
- Bench cuttng through steep bank areas to form new pathway formation
- Temporary Traffic Management (Lane Closure) on works section next to main Aviemore south access road